Marshfield Utilities Combustion Turbine Peak Plant
Construct 52.5 MW combustion turbine peak plant and 115kV substation electrical transmission substation. Concrete foundation for a dual fuel twin jet engine turbine, bolted steel water tank, structural steel pump/maintenance shop, metal substation control building, liquid fuel unloading station, electrical sub grid, & liquid fuel storage tank and containment pit. H-Piling to support electrical grid and turbine engine concrete foundation. Storm sewer drainage system & HDPE/SS/Dual Contained CS process piping system.
CLIENT | City of Marshfield, WI |
DURATION | 2009 – 2010 |
SERVICES | Project Management, Earthwork, Site Utilities, Building, Process Equip & Piping. |
COST | $1.2M |