Grafton Dam – Bridge Street Dam Modifications
Retrofit & modify existing dam to accommodate an added stepped down spillway, hydraulically operated crest weir gate, and the construction of an Architectural overlook and river walk area.
CLIENT | Village of Grafton, Green Bay, WI |
DURATION | Start of Construction June 2013
Project Completion January 2014 |
SERVICES | Earthwork, Earth Retention, Dewatering, Concrete Dams, Process Mechanical |
COST | $1.1 M |